M4 Junction 16 Improvements Project

Uploaded: November 10, 2017

Please be reminded that the remaining overnight closures, to complete surfacing on the A3102 at the Junction 16 roundabout, will be from 13 – 17 November (inclusive) between 20.00 hrs and 06.00 hrs.

As before, the road closure will be from the Junction 16 roundabout to the roundabout for Interface/Woodshaw. Access to all residential and business properties within the closure will be maintained, although this might not necessarily be via your normal route. The approved and signed diversion route, suitable for all through-traffic is below:

We do have contingency dates pencilled in for the following week, 20 – 24 November, in case we encounter any problems which cause delay.